Building Updates

Michael and Anne Greenwood School of Music 

The new building will foster creativity, collaboration and artistic expression, elevating the Department of Music’s tradition of excellence. The Greenwood School of Music’s proximity to The McKnight Center for the Performing Arts will amplify and leverage opportunities, including masterclasses, for students and faculty to interact with world-class musicians. The facility is being designed to encourage collaboration with suites strategically created for specific areas and rehearsal spaces to accommodate varying sizes of music groups. Music laboratories, classrooms and teaching studios will be equipped with the latest technology for high-level studio production. 

Click here to donate

Upcoming Updates for June

  • Complete Exterior Sheathing & Waterproofing
  • Complete Install of Membrane & Flashing on All Roofs
  • Continue Cast Stone & Brick Veneer
  • Continue MEP Rough-In Throughout Building
  • Continue Insterior Framing, Insulation, and Drywall
  • Continue Installing Elevators
  • Continue Curtain Wall Install
  • Continue Installing Single-Skin Metal Panels
  • Continue EIFS at North & West Elevations
  • Begin Installing Roof Access Ladders
  • Begin Installing Barrier Ceiling & Ceiling Grid
  • Begin Installing Composite Metal Panels

Monthly Overview- May 2020

May2020

  • Continued Exterior Framing & Sheathing
  • Continued Exterior Weather Barrier & Board Insulation
  • Continued Cast Stone & Brick Veneer
  • Continued Interior Framing, Insulation, & Drywall
  • Continued MEP Throughout Building
  • Continued Installing Storefront Windows
  • Continued Installing Elevators
  • Started Installing Single-Skin Metal Panels
  • Started Installing EIFS
  • Started Installing Fire Suppression
  • Started Installing The EPDM Roofing
  • Started Installing Curtain Wall System
  • Started Tape & Bed

Aerial View

May Aerial

Click here to view the May Progress Report

Monthly Overview- April 2020

April 2020 Big

  • Completed Reinforcement and Poured SOMD from 2nd Floor to High Roof
  • Completed Reinforcement and Poured 3rd & 4th Floor Topping Slabs
  • Completed INstall of Structural Steel Stringers at North & South Stairs
  • Completed Structural Steel Fireproofing
  • Completed Lightweight Concrete on Roofs
  • Continued Installing Misc. Structural Steel 
  • Continued Exterior Framing, Sheathing, & Weather Barrier
  • Continued Cast Stone & Brick Veneer
  • Continued Interior Framing, Insulation, & Drywall
  • Continued MEP Throughout the Building
  • Continued Installing Storefront Windows
  • Began Installing Elevators

Aerial View

AerialApril

Click here to view the April Progress Report.

Monthly Overview- March 2020

MarchNew

  • Completed Structural Steel North Stair
  • Completed Structural Steel Sourth Stair
  • Began Reinforcing Slab on Metal Decks
  • Began Structural Steel at Elevators
  • Continued CMU Walls
  • Began Installing Cast Stone
  • Began Installing Brick Veneer
  • Continued Exterior Framing & Sheathing
  • Continued Exterior Weather Barrier
  • Continued Interior Framing
  • Continued MEP Throughout Building
  • Began Interior Insulation & Drywall
  • Continued Installing Storefront Windows
  • Began Installing Exterior Board Insulation

Aerial View

AerialClick here to view the March Progress Report 

Construction Progress

Building Progress 

Rehearsal Space

For more information, contact:

Laura Ketchum

Senior Director of Development & Team Lead- College of Arts & Sciences

Oklahoma State University Foundation

o: 405.385.0701 | c: 405.334.2147

e: lketchum@OSUgiving.com